Ningbo Metro Line 2 is expected to reach full line rail transit in June

According to the latest information released by Ningbo Rail Transit group, the back section of phase II of line 2 includes two stations and two sections of Honglian station and Zhaobaoshan station, with a total length of 2.9 kilometers. The track laying works of Houtong section include the track works and ancillary works from Congyuan Road station to Honglian station, with a total length of about 5.91 km.

It is reported that at present, the track laying construction of Houtong section has been completed for 3.72km. In the next step, the construction of jointless track from Honglian station (excluding) to Congyuan Road station, track slab jacking and track fine adjustment will be carried out successively. It is expected to achieve the goal of track connection of the whole line in June.